D-01.06
Report including the description of tasks carried out and technical progress, the related overview of financial status and manpower effort for the METROFOOD-PP project (GA 871083), at Month 12 (June 2020 – Nov. 2020).
It is aimed to the internal quality control of the project, including controlling and monitoring of work package status measured against deliverables and milestone planning, as well as quality and consistency with respect to technical and contractual requirements. An evaluation about main critical points encountered or envisaged and a re-examination of the main risks with related contingency plans (other than - if needed - deviations from the work plan and incidents) were also made.